Cheneys Chapel Stand Alone PV System Profile
Location:Cedar Brush Creek, Australia
Operator:Matt Cheney
Commissioning:9/26/2007
PV system power:13.100 kWp
Annual Production:approx. 12,052 kWh (920 kWh/kWp)
CO2 avoided:Approx. 8.4 tons per annum
Modules:10 x BP Solar 165
30 x Conergy P 190M
22 x TRINA SOLAR
Tracking:Fixed
Communication:Sunny WebBox
Inverter:2 x Sunny Boy 1700
Sunny Boy 4000TL-21
Sunny Island 8.0H
Sunny Mini Central 7000TL
Sensors:2 x Sunny Sensorbox

Description:


Large stand alone system with 13.98 kw solar panels feeding a Sunny Island 8.0H through a Sunny Mini Central 7000, Sunny Boy 4000tl  and 2 x Sunny Boy 1700 with Smartload 6000 as dumploader to pool and hydronic heaters .A Promac 22kva generator is the backup supply.The previous main invereter Sunny Island 4248 has its own 200ah battery bank and is used as a back up system should we have a fault on the main system and will switch all loads in a 100th of a second. All this is monitered via a Sunnywebbox with 2 Sunny  Sensor boxes to keep system at peak