City of Las Vegas - FS41 PV System Profile
Location:Las Vegas, United States
Operator:City of Las Vegas
Commissioning:1/24/2012
PV system power:36.897 kWp
Annual Production:approx. 66,415 kWh (1,800 kWh/kWp)
CO2 avoided:Approx. 46.5 tons per annum
Modules:Canadian Solar Inc. CS5P-235P (UL) (08/2010)
Communication:Sunny WebBox
Inverter:5 x Sunny Boy 4000US
2 x Sunny Boy 7000US
Sunny Island 5048U

Description:


As a part of the City’s Sustainable Energy Strategy, the City has installed more than 4 megawatts of solar, including solar covered parking installations at parks, community centers, and fire stations. Two phases of solar covered parking have been completed, with the first completed in July 2010, totalling 827 kW. The second phase, completed in December 2011, brought the City's total to 1.8 MW of solar covered parking over 1,720 parking spaces.

At Fire Station 41, located in Centennial Hills within Ward 6, panels shade 22 parking spaces. The total size of the system is 36 kW and will generate approximately 72,000 kWh, offsetting the building's meter by about 40 percent. Funding for the project came from New Clean Renewable Energy Bonds and NV Energy SolarGenerations rebates. Contributing to the successful completion of the project was the "design-build" team lead by CORE Construction.